Item Description
Steps taken in the last 7 days
  • Continued maintenance of wildlife fencing and deterrents
  • Continued field screening for EC, chlorides and visual sheen of live trench
  • Continued work to confirm waste management and remediation plans
  • Continued execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
  • Continue maintenance of containment cells for bitumen removal
  • Continued construction activities for removal of damaged section of pipe in support of root cause analysis investigation including fluid recovery as required
Steps anticipated to be taken in the next 7 days
  • Continue maintenance of wildlife fencing and deterrents
  • Continue field screening for EC, chlorides and visual sheen of live trench
  • Continue work to confirm waste management and remediation plans
  • Continue execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
  • Continue maintenance of containment cells for bitumen removal.
  • Continue construction activities for removal of damaged section of pipe in support of root cause analysis investigation including fluid recovery as required
  • Complete removal of damaged section of pipe and prepare for installation of spool piece to allow for required maintenance of the entire produced emulsion pipeline


Return to previous page