Item Description
Steps taken in the last 24 hours
  • Continue activities to facilitate site access
  • Continue stockpiling coconut mats
  • Continue wildlife monitoring
  • Continue fluid recovery of north and south bell hole
  • Field screening for electrical conductivity, chlorides, and visual sheen
  • Updated Comprehensive Plan based on incoming data
  • Continue installation of wildlife fencing
  • Continue installation of wildlife visual deterrents (effigies, tape, pennant flagging)
  • Continue water sampling of unnamed lake and surrounding area
  • Finalized data interpretation of electromagnetic survey, which assists in understanding the location of impacted areas underground
  • Working with the AER on a plan to remove any emulsion from the pipe
Steps to be taken in the next 24 hours
  • Continue activities to facilitate site access
  • Continue stockpiling coconut mats
  • Continue wildlife monitoring
  • Continue fluid recovery of north and south bell hole
  • Continue field screening for electrical conductivity , chlorides, and visual sheen
  • Continue water sampling of unnamed lake and surrounding area
  • Continue wildlife fencing around perimeter of impacted area
  • Finalize and submit Comprehensive Plan to the AER
  • Based on previous data interpretation, install drive point wells in highest risk areas, including the north end of the impacted area
  • Begin excavation of additional sump on north end of the impacted area
  • Continue working with the AER on a plan to remove any emulsion from the pipe