Item Description
Steps taken in the last 24 hours
  • Conducted EM38 and EM31 sweep to delineate impacted area
  • Continue matting site
  • Stockpile coconut mats
  • Wildlife monitoring
  • On-going fluid recovery of north and south bell hole
  • Field screening for EC, chlorides, and visual sheen
  • Environmental Plan drafted and reviewed by AER inspectors at site
  • Wildlife mitigation plan drafted
  • Set up 4 bin tank farm for extra fluid storage (available for use if required)
  • On-going installation of wildlife fence, silt fence, and snow fence
  • Hydrocarbon testing
Steps to be taken in the next 24 hours
  • Obtain sign off from a qualified professional for yesterday’s EM survey results and conduct further EM sweeps
  • Continue matting site
  • Stockpile coconut mats
  • Wildlife monitoring
  • On-going fluid recovery of north and south bell hole
  • Field screening for EC, chlorides, and visual sheen
  • Evolve environmental plan and wildlife mitigation plan as more data becomes available
  • Set up hazmat station
  • Surface water sampling
  • Continue wildlife fencing around perimeter of impacted area
  • String bird deterrent flagging, and install other visual deterrents at site
  • Hydrocarbon testing


Return to previous page