Item Description
Steps taken in the last month
  • Continued maintenance of wildlife fencing
  • Continued work to confirm waste management and remediation plans
  • Continued execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
    • Surface bitumen was previously removed from the spill site
    • Planning for remediation of the remaining bitumen in the underground impacted areas (bitumen seams along the pipeline trenches) is progressing
  • Continued maintenance of containment cells for bitumen removal
  • Completed decommissioning containment cells that are no longer required
  • Confirmed peat material source to support spill site remediation
  • Completed leak test of the produced emulsion line
  • Planning for flushing, pigging and inspection of produced emulsion line
Steps anticipated to be taken in the next month
  • Continue maintenance of wildlife fencing
  • Continue work to confirm waste management and remediation plans
  • Continue execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
    • Commence remediation of the remaining bitumen in the underground impacted areas (bitumen seams along the pipeline trenches)
    • Continue maintenance of containment cells for bitumen removal.
    • Replacement of peat material in pipeline trenches following cleanup efforts
    • Completion of flushing, pigging and inspection activities on the produced emulsion line
    • Leak test of annulus between bulkheads at the pipeline rupture site
    • Assess future plans for the emulsion lines after cleaning and inspection
    • Planning for remediation of pilot plant pond