Item Description
Steps taken in the last 7 days
  • Continued maintenance of wildlife fencing and deterrents
  • Submission to Alberta Health of the Preliminary Quantitative Risk Assessment
  • Continued field screening for EC, chlorides and visual sheen of live trench
  • Continued work to confirm waste management and remediation plans
  • Continued execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
  • Continue maintenance of containment cells for bitumen removal
  • Completed the removal of damaged section of pipe
Steps anticipated to be taken in the next 7 days
  • Completion of winter sampling program for drive point wells and live trench.
  • Continue maintenance of wildlife fencing and deterrents
  • Continue work to confirm waste management and remediation plans
  • Continue execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
  • Continue maintenance of containment cells for bitumen removal
  • Continue activities to prepare for installation of spool piece to allow for required maintenance of the entire produced emulsion pipeline


Return to previous page