Item Description
Steps taken in the last 7 days
  • Continued maintenance of wildlife fencing
  • Continued work to confirm waste management and remediation plans
  • Continued execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
    • Surface bitumen was previously removed from the spill site
    • Planning for remediation of the remaining bitumen in the underground impacted areas (bitumen seams along the pipeline trenches) is progressing
    • Continued maintenance of containment cells for bitumen removal
    • Began decommissioning containment cells no longer required
    • 24 hour monitoring program implemented for proposed leak test on the produced emulsion line
    Steps anticipated to be taken in the next 7 days
    • Continue maintenance of wildlife fencing
    • Continue work to confirm waste management and remediation plans
    • Continue execution and waste management activities for removal of bitumen at the spill site, including off-site disposal
      • Planning for remediation of the remaining bitumen in the underground impacted areas (bitumen seams along the pipeline trenches) is progressing
      • Continue maintenance of containment cells for bitumen removal.
      • Continue decommissioning containment cells no longer required
      • Completion of the leak test and discontinuation of the 24 hour monitoring program on the produced emulsion line