Item Description
Steps taken in the last 24 hours
  • Emulsion recovery from pipeline
  • Continued wildlife monitoring, including pit fall traps
  • No impacted wildlife reported
  • Fluid recovery of bell holes and recovery trench on going
  • Continued field screening for EC, chlorides, and visual sheen
  • Maintenance of wildlife fencing and deterrents
  • Continue to move visual deterrents to prevent habituation
  • Continued priority water sampling of Unnamed Lake and surrounding area
  • Collected subsurface water samples from all drive point wells
  • Completed aquatic assessment of lake NE of site
  • Field trials for waste management options
  • Completed additional bell hole in SW and extension of north portion of existing trench
Steps to be taken in the next 24 hours
  • Continue emulsion recovery from pipeline
  • Continue wildlife monitoring, including pit fall traps
  • Continue to move visual deterrents to prevent habituation
  • Continue fluid recovery of bell holes and recovery trench after pipeline activities conclude
  • Continue priority field screening for EC, chlorides, and visual sheen, surface water sampling, subsurface water sampling, and soil sampling
  • Continue priority water sampling of Unnamed Lake and surrounding area
  • Continue field trials to confirm waste management and remediation plans
  • Continue subsurface water samples from all drive point wells