Item Description
Steps taken in the last 72 hours
  • Continued wildlife monitoring, including pit fall traps
  • Continued maintenance of wildlife fencing and deterrents
  • Continue to move visual deterrents to prevent habituation
  • Continued fluid recovery of bell holes and recovery trench including four new shallow recovery bell holes
  • Continued field screening for EC, chlorides, and visual sheen
  • Continued priority water sampling of Unnamed Lake and surrounding area
  • Collected subsurface water samples from all drive point wells
  • Continued work to confirm waste management and remediation plans
  • Continued construction of the dewatering facility at the Pilot Plant
  • Completed culvert installation for matted access road
  • One wood frog was deceased as a result of the spill
Steps anticipated to be taken in the next 48 hours
  • Continue wildlife monitoring, including pit fall traps
  • Continue maintenance of wildlife fencing and deterrents
  • Continue to move visual deterrents to prevent habituation
  • Continue fluid recovery of bell holes and recovery trench including four new shallow recovery bell holes
  • Continue field screening for EC, chlorides, and visual sheen
  • Continue priority water sampling of Unnamed Lake and surrounding area
  • Continue subsurface water samples from all drive point wells
  • Continue work to confirm waste management and remediation plans
  • Continue construction of the dewatering facility at the Pilot Plant
  • Convert west recovery trench to live trench for seasonal chloride recovery, if approved by the AER